Hello
everyone, long time no read.
I’d like to
share with you a story on my fatigue tests. As you know, fatigue of R-UHPFC
beams is the main topic of my research (if you don’t remember what this
abbreviation stands for, check my previous posts!)
Do you
remember that I was doing some tests in cooperation with Antoine? The first
beam instrumented with his Fibre Optics we've tested back in December under quasi-static
loading. This was done mostly to calibrate the future fatigue load levels.
Then, the
fatigue test followed. We have started it just before Christmas (in fact, we
started to run it a day before Antoine left for his holidays, and two days
before I have left for mine). The plan was to run it for some three to four
weeks continuously. Thanks to internet, we were controlling everything in the
lab in Lausanne, while he was in Lebanon and me in Poland. That’s the real globalisation!
But, on
December 27th, the localized crack under the force application point has
passed through one of the fibres in the upper flange. We've become ‘blind’ from
this section on. Thus, we have had to temporarily stop the test. In
mid-January, when both of us were back in Lausanne, we have re-connected and
re-calibrated the fibre. The test continued.
In the
beginning of February, strange thing happened. The jack could not produce
anymore the force we wanted. Thus, we had to remove it without touching the
sensors, not to de-calibrate them. That was like a surgery on an open heart, but
our technicians are experts.
The jack
was sent to the company for check-up. The reason of failure was… fatigue of one of the elements inside
of the piston! After reparation, which took some 3 weeks, and re-installation
on the testing rig (another week of work), in the beginning of March we have
picked up the test. But, after just 2 days, the jack failed again!
Unfortunately, during reparation, they have made a small mistake in the
assembly. This meant another month of delay for me…
Finally, in
the first days of April, the jack was installed again and the test continued.
After another 2 weeks, on the 15th of April, circa 8AM, the beam failed!
And so, after almost 4 months and 6.5 million of cycles, we have finished the
test. It took some 3 months longer than planned!
I am writing
this to show that the research is not only a success story. There are many
things that can go wrong. Some of them depend on us; on some we don’t have any
influence. Of course, it’s us who decide how to deal with the problems… and how
to manage the time not to waste it! And, trust me, during these 4 months I’ve
had plenty of other topics to work on ;).
Back in
2017, when I was starting my research, one of the experts has told me: ‘the
fatigue experiments are very… fatiguing’. Believe me, he was right.