In the last post I was informing you about preparation of the casting campaign.
Now, my own small factory is fully operational, including:
Mixing,
casting... with use of external vibrators!
curing for 7 days in formworks,
demoulding, labeling,
...and finally moving to the storage area.
In July I have reached efficiency of 3 beams per week, which is a good result.
Unfortunately, I am not that good in taking videos with my cell phone... or maybe this post was just optimised for your mobiles? ;)
Now, the beams are awaiting for my test setup to be ready. This should happen within a week or two.
So, stay tuned!